How to forecast tasks?
|
||||
======================
|
||||
======================
|
||||
|
||||
Introduction to forecast
|
||||
========================
|
||||
|
||||
Scheduling and forecasting tasks is another way to manage projects. In
|
||||
Odoo, the Forecast option gives you access to the Gantt chart.
|
||||
|
||||
So far, you've been working with the Kanban view, which shows you the
|
||||
progress of a project and its related tasks.
|
||||
|
||||
Now, with the Forecast option, the Gantt view gives you the big picture.
|
||||
It's highly visual which is a real plus for complex projects, and it
|
||||
helps team members to collaborate better.
|
||||
|
||||
This option is a real benefit in terms of planning and organizing the
|
||||
workload and human resources.
|
||||
|
||||
How to configure the projects?
|
||||
==============================
|
||||
|
||||
Configure the project application
|
||||
---------------------------------
|
||||
|
||||
The **Forecast** option helps you to organize your projects. This is perfect
|
||||
when you need to set up a project with a specific deadline. Therefore,
|
||||
each task is assigned a specific timeframe (amount of hours) in which
|
||||
your employee should complete it!
|
||||
|
||||
First you need to activate the **Forecast** option for the whole project
|
||||
application:
|
||||
|
||||
Go to :menuselection:`Project --> Configuration --> Settings`.
|
||||
Select the Forecast option and click **Apply**.
|
||||
|
||||
.. image:: media/forecast01.png
|
||||
:align: center
|
||||
|
||||
Once this is done, you still need to activate the **Forecast** option
|
||||
specifically for your **Project** (maybe you don't need the Gantt chart for
|
||||
all the projects that you manage).
|
||||
|
||||
Configure a specific project.
|
||||
-----------------------------
|
||||
|
||||
When creating a new project, make sure to select the option "Allow
|
||||
Forecast" in your project settings.
|
||||
|
||||
You'll see the **Forecast** option appearing in the top menu.
|
||||
|
||||
.. image:: media/forecast02.png
|
||||
:align: center
|
||||
|
||||
If you add the Forecasting option to an existing project, whether there
|
||||
are task deadlines or not scheduled, the task won't be displayed.
|
||||
|
||||
The tasks of a project are not related to a forecast.
|
||||
|
||||
How to create a forecast?
|
||||
-------------------------
|
||||
|
||||
Before creating a project with forecast, list all the tasks with the
|
||||
projected time they should take. It will help you to coordinate the
|
||||
work.
|
||||
|
||||
In order to display the projects in the Gantt chart, you need to create
|
||||
the forecast from the task page. To create a forecast, click on the top
|
||||
left corner of the task, **Create a Forecast**.
|
||||
|
||||
.. image:: media/forecast03.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
You can also create a new Forecast easily by directly clicking on an empty
|
||||
space in the Gantt chart calendar.
|
||||
|
||||
The Forecast interface will fill in the name of the Project and the task
|
||||
automatically. You just need to add the dates and the time the task
|
||||
should take.
|
||||
|
||||
.. image:: media/forecast04.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
The "Effective hours" field appears only if you have the **Timesheet** app
|
||||
installed on your database. This option helps you to see the progress of a
|
||||
task thanks to the integration with Timesheet.
|
||||
|
||||
For example: When a user fills in a Timesheet with your Project name
|
||||
(Analytic account), with 10 hours spent, the forecast will display 10 hours
|
||||
in the Estimated Time field.
|
||||
|
||||
What are the difference between the views?
|
||||
==========================================
|
||||
|
||||
In the **Project** app menu you have a **Forecast** menu. This sub-menu helps
|
||||
you to see the Gantt chart from different points of view: by users or by
|
||||
projects.
|
||||
|
||||
By users : people management
|
||||
----------------------------
|
||||
|
||||
This option displays the Gantt chart with the people assigned. Odoo's
|
||||
Gantt chart shows you who's involved; it gives you the big picture of
|
||||
the project. It's very useful to allocate your resources effectively.
|
||||
|
||||
On the left side, first level, you can see which users are involved.
|
||||
Then, on the second level you see which projects they are assigned to.
|
||||
On the third, you see which tasks they're on.
|
||||
|
||||
Each task is represented by a coloured rectangle. This rectangle
|
||||
reflects the duration of the task in the calendar.
|
||||
|
||||
The top rectangle on the first level is the sum of all the tasks
|
||||
compiled from the third level. If it's green, it means that the total
|
||||
time allocated to that user is less than 100%. When it's red, it means
|
||||
that this user is assigned to multiple tasks which total more than 100%
|
||||
of his/her time.
|
||||
|
||||
.. image:: media/forecast05.png
|
||||
:align: center
|
||||
|
||||
Plan the workload
|
||||
~~~~~~~~~~~~~~~~~
|
||||
|
||||
When creating a forecast, you have to select the time the user should
|
||||
spend on it. 100% means that your user should work on it full time
|
||||
during those days. He/She has no other tasks to work on. So you can
|
||||
decide from 1 to 100% how your users should organize their time between
|
||||
different tasks.
|
||||
|
||||
The power of integration helps you to avoid double booking an employee.
|
||||
For example, if your expert is already at 40% on another task in another
|
||||
project, you can book him/her for only 60% for that period.
|
||||
|
||||
In the example below, the user "Administrator" is working on 2 projects
|
||||
("IT1367 Delivery Phases" and "Implementation Process56"). The user is
|
||||
assigned to both projects with a total of 110% of their time. This is
|
||||
too much so the Project Manager should change the users assigned to the
|
||||
task. Otherwise, the PM can change the dedicated time or the dates, to
|
||||
make sure that this is feasible.
|
||||
|
||||
.. image:: media/forecast06.png
|
||||
:align: center
|
||||
|
||||
Gantt view advantages
|
||||
~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
This Gantt view ‘by user' helps you to better plan your human resources.
|
||||
You avoid confusion about the the tasks and the assignations of the
|
||||
users. The Gantt Chart is highly visual and helps to comprehend all the
|
||||
different elements at once. Also, you immediately know what has to be
|
||||
done next. This method helps you to better understand the relations
|
||||
between the tasks.
|
||||
|
||||
The dynamic view of the Gantt in Odoo allows you to:
|
||||
|
||||
- change the time and date of a forecast by clicking and sliding the
|
||||
tasks in the future or in the past
|
||||
|
||||
- create a new forecast into the Gantt chart immediately
|
||||
|
||||
- modify an existing forecast
|
||||
|
||||
- change the length of a task by extending or shortening the rectangle.
|
||||
|
||||
By projects: project management
|
||||
-------------------------------
|
||||
|
||||
The Gantt Chart is the perfect view of a project to better understand
|
||||
the interactions between the tasks. You can avoid overlapping tasks or
|
||||
starting one too early if another one isn't finished. Odoo Gantt chart
|
||||
is clear and helps you to coordinate tasks efficiently.
|
||||
|
||||
This option displays the Gantt chart by showing the projects on the
|
||||
first level of hierarchy.
|
||||
|
||||
On the left side, first level, you can see the projects. Then, on the
|
||||
second level you see which users are assigned. On the third, you see
|
||||
which tasks they're on.
|
||||
|
||||
This view won't show your HR time. The colours don't apply. (see **By
|
||||
Users** section)
|
||||
|
||||
.. image:: media/forecast07.png
|
||||
:align: center
|
||||
|
||||
Gantt view advantages
|
||||
~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
The dynamic view of the Gantt in Odoo allows you to:
|
||||
|
||||
- change the time and date of a forecast by clicking and sliding the
|
||||
tasks in the future or in the past
|
||||
|
||||
- create a new forecast into the Gantt chart immediately
|
||||
|
||||
- modify an existing forecast
|
||||
|
||||
- change the length of a task by extending or shortening the rectangle.
|
||||
|
||||
|
After Width: | Height: | Size: 54 KiB |
|
After Width: | Height: | Size: 61 KiB |
|
After Width: | Height: | Size: 12 KiB |
|
After Width: | Height: | Size: 9.8 KiB |
|
After Width: | Height: | Size: 12 KiB |
|
After Width: | Height: | Size: 14 KiB |
|
After Width: | Height: | Size: 13 KiB |