Using an alternative Work Center
|
||||
================================
|
||||
|
||||
For many manufacturing companies, a common issue is to have to
|
||||
manufacture, at the same time, several products usually produced at the
|
||||
same work center. If in practice, employees can manufacture the goods at
|
||||
another work center, it is not that simple.
|
||||
|
||||
You need to keep track of the job: which work center has been used and
|
||||
when, so you can schedule maintenance efficiently. With Odoo, you can
|
||||
configure it so you can keep tracking manufacturing orders and your
|
||||
employees have an alternative work center to use.
|
||||
|
||||
This way, your process becomes more efficient, and less non-productive
|
||||
time will be noticed.
|
||||
|
||||
|
||||
Configure your Work Centers
|
||||
===========================
|
||||
|
||||
The first thing to do is to go to the *Manufacturing* app settings.
|
||||
Then, enable the *Work Orders* feature and hit save.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_01.png
|
||||
:align: center
|
||||
|
||||
|
||||
Now, go to the *Work Centers* menu under *Master Data* and create
|
||||
two new work centers. Add the second work centers as an alternative to
|
||||
the first and vice versa.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_02.png
|
||||
:align: center
|
||||
|
||||
|
||||
The next step is to create your *routing*. Add your work center and an
|
||||
operation to it before saving.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_03.png
|
||||
:align: center
|
||||
|
||||
|
||||
Then, you can create your *Bill of Materials* and add components and
|
||||
routing to it.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_04.png
|
||||
:align: center
|
||||
|
||||
|
||||
Create your Work Orders
|
||||
=======================
|
||||
|
||||
Now that everything is configured, you can create your *Work Orders*.
|
||||
Go to the *Manufacturing Orders* menu and hit *Create*. There, add
|
||||
your product and plan it. In the *Work Orders* list, you can find it
|
||||
ready to be assembled.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_05.png
|
||||
:align: center
|
||||
|
||||
|
||||
Each new *Work Order*, which will be created before the end of the
|
||||
first one, will be scheduled at the alternative work center you
|
||||
configured.
|
||||
|
||||
|
||||
.. image:: media/alternative_wc_06.png
|
||||
:align: center
|
||||
|
||||
|
||||
.. note::
|
||||
Keep in mind that, if you add time after production to your work center,
|
||||
you may have work orders scheduled for your alternative work center even
|
||||
if the usual one is free.
|
||||
@@ -1,140 +1,91 @@
|
||||
=================================
|
||||
How to create a Bill of Materials
|
||||
=================================
|
||||
|
||||
A bill of materials (BoM) is a document that describes the component
|
||||
products, the quantity of each component, and the process required to
|
||||
manufacture a product, including a routing and individual steps.
|
||||
|
||||
In Odoo, each product may have multiple BoMs associated with it, but a
|
||||
BoM can only be associated with a single product. A single BoM can,
|
||||
however, describe multiple variants of the same product.
|
||||
|
||||
Setting up a Basic BoM
|
||||
======================
|
||||
|
||||
If you choose to manage your manufacturing operations using manufacturing
|
||||
orders only, you will define basic bills of materials without routings.
|
||||
|
||||
Before creating your first bill of materials, you will need to create a
|
||||
product and at least one component (components are considered products
|
||||
in Odoo). You can do so from :menuselection:`Master Data --> Products`, or
|
||||
on the fly from the relevant fields on the BoM form. Review the
|
||||
Inventory chapter for more information about configuring products. Once
|
||||
you have created a product and at least one component, select them from
|
||||
the relevant dropdown menus to add them to your bill of materials. A new
|
||||
bill of materials can be created from :menuselection:`Master Data --> Bills of Materials`,
|
||||
or using the button on the top of the product form.
|
||||
|
||||
Under the **Miscellaneous** tab, you can fill additional fields.
|
||||
**Sequence** defines the order in which your BoMs will be selected
|
||||
for production orders, with lower numbers having higher priority.
|
||||
**Version** allows you to track changes to your BoM over time.
|
||||
|
||||
Adding a Routing to a BoM
|
||||
=========================
|
||||
Create Bills of Materials
|
||||
=========================
|
||||
|
||||
A routing defines a series of operations required to manufacture a
|
||||
product and the work center at which each operation is performed. A
|
||||
routing may be added to multiple BoMs, though a BoM may only have one
|
||||
routing. For more information about configuring routings, review the
|
||||
chapter on routings.
|
||||
A *Bill of Materials* is a document defining the quantity of each
|
||||
component required to manufacture a finished product. It also includes
|
||||
the routing and individual steps of the manufacturing process.
|
||||
|
||||
After enabling routings from :menuselection:`Configuration --> Settings`,
|
||||
you will be able to add a routing to a bill of materials by selecting a
|
||||
routing from the dropdown list or creating one on the fly.
|
||||
With Odoo, you can link multiple BoMs to each product and use it to
|
||||
describe multiple variants of them. Each BoM will, yet, be associated
|
||||
with one product only.
|
||||
|
||||
You may define the work operation or step in which each component is
|
||||
consumed using the field, **Consumed in Operation** under the
|
||||
**Components** tab. Similarly, you can define the operation at which the
|
||||
product will be produced under the **Miscellaneous** tab using the field
|
||||
**Produced at Operation**. If this field is left blank, the products
|
||||
will be consumed/produced at the final operation in the routing.
|
||||
This feature will help optimize your manufacturing process while saving
|
||||
you time.
|
||||
|
||||
.. image:: media/bill_configuration01.png
|
||||
Setting up a BoM
|
||||
================
|
||||
|
||||
You can use BoMs without routings. You will use this if you choose to
|
||||
manage your manufacturing operations using manufacturing orders only. In
|
||||
other words, you choose to realize your manufacturing process in one
|
||||
step and do not track the steps the product goes through.
|
||||
|
||||
Before creating your *BoM*, you have to create the product using the
|
||||
*BoM* and, at least, one of the components. Go to the *Master Data*
|
||||
menu > *Products* and create both the finished product and the
|
||||
component.
|
||||
|
||||
Once done, go to the *Bills of Materials* menu under *Master Data*.
|
||||
Now, create it. Choose the product from the dropdown menu and add your
|
||||
components and the quantity. In this case, keep the default *BoM*
|
||||
type, which is *Manufacture this Product*.
|
||||
|
||||
.. image:: media/bills_of_materials_01.png
|
||||
:align: center
|
||||
|
||||
Adding Byproducts to a BoM
|
||||
==========================
|
||||
Using the same BoM to describe Variants
|
||||
---------------------------------------
|
||||
|
||||
In Odoo, a byproduct is any product produced by a BoM in addition to the
|
||||
primary product.
|
||||
As said above, you can use *BoM* for *Product Variants*. It is
|
||||
basically the same as for the standard product.
|
||||
|
||||
To add byproducts to a BoM, you will first need to enable them from
|
||||
:menuselection:`Configuration --> Settings`.
|
||||
If your *BoM* is for one variant only, then specify which one in the
|
||||
*Product Variant* field. If not, specify the variant it is consumed
|
||||
for on each component line. You can add several variants for each
|
||||
component.
|
||||
|
||||
.. image:: media/bill_configuration02.png
|
||||
.. image:: media/bills_of_materials_02.png
|
||||
:align: center
|
||||
|
||||
Once byproducts are enabled, you can add them to your bills of materials
|
||||
under the **Byproducts** tab of the bill of materials. You can add
|
||||
any product or products as byproducts. Byproducts are produced in the
|
||||
same step of the routing as the primary product of the BoM.
|
||||
Adding a routing
|
||||
================
|
||||
|
||||
.. image:: media/bill_configuration03.png
|
||||
You can add routing to your *BoM*. You will do this if you need to
|
||||
define a series of operations required by your manufacturing process. To
|
||||
use it, enable the *Work Orders* feature in the *Manufacturing* app
|
||||
settings.
|
||||
|
||||
.. image:: media/bills_of_materials_03.png
|
||||
:align: center
|
||||
|
||||
Setting up a BoM for a Product With Sub-Assemblies
|
||||
==================================================
|
||||
.. note::
|
||||
Each *BoM* can have only one routing while each routing can be used
|
||||
multiple times.
|
||||
|
||||
A subassembly is a manufactured product which is intended to be used as
|
||||
a component of another manufactured product. You may wish to employ
|
||||
sub-assemblies to simplify a complex BoM, to more accurately represent
|
||||
your manufacturing flow, or to use the same subassembly in multiple
|
||||
BoMs. A BoM that employs subassemblies is often referred to as a
|
||||
multi-level BoM.
|
||||
Now that you have created your routing, add it to your *BoM*. You can
|
||||
select when, in the work operations, your components are consumed with
|
||||
the dropdown menu.
|
||||
|
||||
Multi-level bills of materials in Odoo are accomplished by creating a
|
||||
top-level BoM and subassembly BoMs. Next, the procurement route of the
|
||||
subassembly product is defined. This ensures that every time a
|
||||
manufacturing order for the top-level product is created, a
|
||||
manufacturing order for each subassembly is created as well.
|
||||
|
||||
Configure the Top-Level Product BoM
|
||||
-----------------------------------
|
||||
|
||||
To configure a multi-level BoM, create the top-level product and its
|
||||
BoM. Include any subassemblies in the list of components. Create a BoM
|
||||
for each subassembly as you would for any product.
|
||||
|
||||
.. image:: media/bill_configuration04.png
|
||||
.. image:: media/bills_of_materials_04.png
|
||||
:align: center
|
||||
|
||||
Configure the Subassembly Product Data
|
||||
--------------------------------------
|
||||
Adding By-Products
|
||||
==================
|
||||
|
||||
On the product form of the subassembly, you must select the routes
|
||||
**Manufacture** and **Make To Order**. The **Manufacture**
|
||||
route takes precedence over the **Buy** route, so selecting the
|
||||
latter will have no effect.
|
||||
In Odoo, a *by-product* is any product produced by a *BoM* in
|
||||
addition to the primary product.
|
||||
|
||||
.. image:: media/bill_configuration05.png
|
||||
To add *by-products* to a *BoM*, you will first need to enable them
|
||||
from the *Manufacturing* app settings.
|
||||
|
||||
.. image:: media/bills_of_materials_05.png
|
||||
:align: center
|
||||
|
||||
If you would like to be able to purchase the subassembly in addition to
|
||||
manufacturing it, select **Can be Purchased**. All other fields on
|
||||
the subassembly product form may be configured according to your
|
||||
preference.
|
||||
Once the feature is enabled, you can add your *By-Products* to your
|
||||
*BoMs*. You can add as many *By-Products* as you want. Just keep in
|
||||
mind that you need to register during which operation your by-product is
|
||||
produced.
|
||||
|
||||
Using a Single BoM to Describe Several Variants of a Single Product
|
||||
===================================================================
|
||||
|
||||
Odoo allows you to use one bill of materials for multiple variants of
|
||||
the same product. Simply enable variants from
|
||||
:menuselection:`Configuration --> Settings`.
|
||||
|
||||
.. image:: media/bill_configuration06.png
|
||||
:align: center
|
||||
|
||||
You will then be able to specify which component lines are to be used in
|
||||
the manufacture of each product variant. You may specify multiple
|
||||
variants for each line. If no variant is specified, the line will be
|
||||
used for all variants.
|
||||
|
||||
When defining variant BoMs on a line-item-basis, the **Product
|
||||
Variant** field in the main section of the BoM should be left blank.
|
||||
This field is used when creating a BoM for one variant of a product
|
||||
only.
|
||||
|
||||
.. image:: media/bill_configuration07.png
|
||||
:align: center
|
||||
.. image:: media/bills_of_materials_06.png
|
||||
:align: center
|
||||
@@ -0,0 +1,53 @@
|
||||
===================================
|
||||
Use flexible components consumption
|
||||
===================================
|
||||
|
||||
Sometimes, you might need more components than usual to manufacture a
|
||||
product. Let’s say that you produce a desk combination of 4 desks and
|
||||
two chairs but your customer asks you one more desk. Alright, you can do
|
||||
that. But you will need to register it!
|
||||
|
||||
In case this happens, Odoo has the *flexible components consumption*
|
||||
feature available. If you enable it, you will be able to consume as many
|
||||
components as needed and it will make you save time in the registration
|
||||
of your items consumption.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
Using flexible component consumption is easy and can be done in a few
|
||||
steps. All you need is a *BoM* and a *Quality Control Point*.
|
||||
Therefore, you will need to activate the feature *Quality* in the
|
||||
*MRP* app settings.
|
||||
|
||||
First, open the *BoM* you want to use for flexible component
|
||||
consumption and edit it. In the *Miscellaneous* tab, choose
|
||||
*Flexible* as the consumption type. Then, save.
|
||||
|
||||
.. image:: media/flexible_components_consumption_01.png
|
||||
:align: center
|
||||
|
||||
Now, in the *Quality* app, open the *Control Point* menu, under
|
||||
*Quality Control* and create a new *Quality Control Point*. Choose
|
||||
your product, your operation and work order operation. Then, choose
|
||||
*Register Consumed Materials* as type.
|
||||
|
||||
.. image:: media/flexible_components_consumption_02.png
|
||||
:align: center
|
||||
|
||||
Next, go back to your *Manufacturing* app and create a *Manufacturing
|
||||
order*. Choose the product for which you have created the flexible
|
||||
*BoM*.
|
||||
|
||||
Then, confirm it and launch the process step. While processing, you will
|
||||
have the possibility to consume more components than expected in the
|
||||
*BoM*. To do so, click on *Continue Consumption*.
|
||||
|
||||
.. image:: media/flexible_components_consumption_03.png
|
||||
:align: center
|
||||
|
||||
When the job is over, you will find a summary of your component
|
||||
consumption in the *Finished Steps* tab of your work order.
|
||||
|
||||
.. image:: media/flexible_components_consumption_04.png
|
||||
:align: center
|
||||
@@ -1,80 +1,81 @@
|
||||
======================================
|
||||
How to Sell a Set of Products as a Kit
|
||||
======================================
|
||||
=============================
|
||||
Sell sets of products as kits
|
||||
=============================
|
||||
|
||||
A *kit* is a set of components that are delivered without first being
|
||||
assembled or mixed. Kits are described in Odoo using *bills of
|
||||
materials*. There are two basic ways to configure kits, depending on
|
||||
how stock of the kit product is to be managed. In either case, both the
|
||||
Inventory and Manufacturing apps must be installed.
|
||||
assembled or mixed. *Kits* are described in Odoo using *Bills of
|
||||
Materials*. There are two basic ways to configure *kits*, depending
|
||||
on how the stock of the kit product is to be managed. In either case,
|
||||
both the *Inventory* and *Manufacturing* apps must be installed.
|
||||
|
||||
Manage Stock of Component Products
|
||||
==================================
|
||||
|
||||
If you would like to assemble kits as they are ordered, managing stock
|
||||
of the kit *components* only, you will use a Kit BoM without a
|
||||
manufacturing step.
|
||||
If you want to assemble kits as they are ordered, managing stock of the
|
||||
kit components only, you will use a *Kit BoM* without a manufacturing
|
||||
step.
|
||||
|
||||
A product using a Kit BoM will appear as a single line item on a
|
||||
A product using a *Kit BoM* will appear as a single line item on a
|
||||
quotation and sales order, but will generate a delivery order with one
|
||||
line item for each of the components of the kit. In the examples below,
|
||||
the image at left shows a sales order for the kit "Custom Computer Kit",
|
||||
while the image at right shows the corresponding delivery order.
|
||||
the first image shows a sales order for the kit *Custom Computer Kit*,
|
||||
while the second image shows the corresponding delivery order.
|
||||
|
||||
|image0|\ |image1|
|
||||
|
||||
Configuration
|
||||
-------------
|
||||
|
||||
From the **Products** menu in either the Inventory or Manufacturing
|
||||
app, create each component product as you would any other product, then
|
||||
create the top-level, or kit product. The kit product should have only
|
||||
the route **Manufacture** set. Because you cannot track the stock of
|
||||
kit products, the Product Type should be set to **Consumable**.
|
||||
Because a kit product cannot be purchased, **Can be Purchased**
|
||||
should be unchecked.
|
||||
|
||||
All other parameters on the kit product may be modified according to
|
||||
your preference. The component products require no special
|
||||
configuration.
|
||||
|
||||
.. image:: media/kit_shipping03.png
|
||||
.. image:: media/kit_shipping_01.png
|
||||
:align: center
|
||||
|
||||
Once the products are configured, create a bill of materials for the kit
|
||||
product. Add each component and its quantity. Select the BoM Type
|
||||
**Ship this product as a set of components**. All other options may
|
||||
be left with their default values.
|
||||
.. image:: media/kit_shipping_02.png
|
||||
:align: center
|
||||
|
||||
.. image:: media/kit_shipping04.png
|
||||
Configuration
|
||||
=============
|
||||
|
||||
From the *Products menu* in either the *Inventory* or
|
||||
*Manufacturing* app, create each component product as you would with
|
||||
any other product, then create the top-level, or kit product. The kit
|
||||
product should have only the *route Manufacture* set, in the
|
||||
*Inventory tab*. Because you cannot track the stock of kit products,
|
||||
the *Product Type* should be set to Consumable. Because a kit product
|
||||
cannot be purchased, then, *Can be Purchased* should be unchecked.
|
||||
|
||||
All other parameters on the kit product may be modified according to
|
||||
your preference. The component products require no particular
|
||||
configuration.
|
||||
|
||||
.. image:: media/kit_shipping_03.png
|
||||
:align: center
|
||||
|
||||
Once the products are configured, create a *bill of materials* for the
|
||||
kit product. Add each component and its quantity. Select the *BoM Type
|
||||
Ship this product as a set of components*. All other options may be
|
||||
left with their default values.
|
||||
|
||||
.. image:: media/kit_shipping_04.png
|
||||
:align: center
|
||||
|
||||
Manage Stock of Kit Product and Component Products
|
||||
==================================================
|
||||
|
||||
If you would like to manage stock of the top-level kit product, you will
|
||||
use a standard BoM with a manufacturing step instead of a Kit BoM. When
|
||||
using a standard BoM to assemble kits, a manufacturing order will be
|
||||
created. The manufacturing order must be registered as completed before
|
||||
the kit product will appear in your stock.
|
||||
If you want to manage stock of the *top-level kit product*, you will
|
||||
use a standard *BoM* with a manufacturing step instead of a *Kit
|
||||
BoM*. When using a standard BoM to assemble kits, a *manufacturing
|
||||
order* will be created. The *manufacturing order* must be registered
|
||||
as completed before the kit product will appear in your stock.
|
||||
|
||||
Configuration
|
||||
-------------
|
||||
=============
|
||||
|
||||
On the kit product, select the route **Manufacture**. You may also
|
||||
select **Make to Order**, which will create a manufacturing order
|
||||
whenever a sales order is confirmed. Select the product type
|
||||
**Stockable Product** to enable stock management.
|
||||
On the kit product, select the *route Manufacture*. You may also
|
||||
select *Make to Order*, which will create a *manufacturing order*
|
||||
whenever a sales order is confirmed. Select the product type *Storable
|
||||
Product* to enable stock management.
|
||||
|
||||
.. image:: media/kit_shipping05.png
|
||||
.. image:: media/kit_shipping_05.png
|
||||
:align: center
|
||||
|
||||
When you create the bill of materials, select the BoM Type
|
||||
**Manufacture this product**. The assembly of the kit will be
|
||||
described by a manufacturing order rather than a packing operation.
|
||||
When you create the *bill of materials*, select the BoM Type
|
||||
*Manufacture this product*. The assembly of the kit will be described
|
||||
by a *manufacturing order* rather than a packing operation.
|
||||
|
||||
.. image:: media/kit_shipping06.png
|
||||
:align: center
|
||||
|
||||
.. |image0| image:: ./media/kit_shipping01.png
|
||||
.. |image1| image:: ./media/kit_shipping02.png
|
||||
.. image:: media/kit_shipping_06.png
|
||||
:align: center
|
||||
@@ -1,56 +1,75 @@
|
||||
====================================
|
||||
How to process a manufacturing order
|
||||
====================================
|
||||
============================
|
||||
Process Manufacturing Orders
|
||||
============================
|
||||
|
||||
Introduction
|
||||
============
|
||||
In Odoo, you can manage your manufacturing process in two different
|
||||
ways. You can work with one document, or decide to have more information
|
||||
and control over it.
|
||||
|
||||
There are two basic ways to manage manufacturing in Odoo. The first way
|
||||
manages work with one document only. This document is the
|
||||
**manufacturing order**. The second way uses additional documents to
|
||||
give you more precise control over the manufacturing process. In this
|
||||
way, **Manufacturing orders** are divided into one or more steps
|
||||
defined by **work orders**, performed in an order defined by
|
||||
**routings**.
|
||||
In the first case, Odoo makes things easier and helps you manage work
|
||||
with one document only: the manufacturing order. No complex steps during
|
||||
the process, you just have to schedule the job and record the
|
||||
production.
|
||||
|
||||
How to manage manufacturing without routings
|
||||
============================================
|
||||
But, if you need more control, you can use additional documents (steps)
|
||||
to your manufacturing process. This way, *Manufacturing Orders* are
|
||||
divided into one or more steps defined by *Work Orders* and performed
|
||||
in a sequence defined by *routings*.
|
||||
|
||||
You will most likely use manufacturing orders without routings if all
|
||||
the work to produce your product is performed in one place, by one
|
||||
person, in one step, and/or you do not need the level of granular
|
||||
control afforded by work orders and routings.
|
||||
Using Odoo will allow you to precisely schedule the job, analyze your
|
||||
efficiency but also have ease when realizing each step of your
|
||||
manufacturing process.
|
||||
|
||||
Managing your operations in this way is the default behavior in Odoo.
|
||||
There are two basic phases from planning to production:
|
||||
Manage Manufacturing Without Routings
|
||||
=====================================
|
||||
|
||||
1. Create manufacturing orders
|
||||
If your manufacturing process is limited to one place, one person and
|
||||
one step, you will probably use manufacturing orders without routings.
|
||||
|
||||
2. Record Production
|
||||
In Odoo, it is the default behavior. If work this way, there are two
|
||||
basic phases from planning to production:
|
||||
|
||||
How to manage manufacturing with routings and work orders
|
||||
=========================================================
|
||||
- Create a manufacturing order
|
||||
|
||||
To use work orders and routings, you will need to enable the option
|
||||
**Manage production by work orders** From
|
||||
:menuselection:`Configuration --> Settings`. You will then be able to add
|
||||
routings to bills of materials, and configure some additional related
|
||||
fields. You will also be able to create **work centers**, the
|
||||
- Record the production
|
||||
|
||||
Manage Manufacturing with Routings and Work Centers
|
||||
===================================================
|
||||
|
||||
To use *Work Centers* and *Routings*, you will need to enable the
|
||||
*Work Orders* feature. To do so, go to the *Manufacturing* app
|
||||
settings.
|
||||
|
||||
.. image:: media/process_manufacturing_orders_01.png
|
||||
:align: center
|
||||
|
||||
Now, you can add routings to *BoMs* and configure your operations
|
||||
taking place at different *work centers*. The *Work Centers* are the
|
||||
locations at which work orders are performed.
|
||||
|
||||
When manufacturing with routings and work orders, each work order is
|
||||
scheduled individually. You will also have access to time and capacity
|
||||
planning, and reports on costing and efficiency on a work center level.
|
||||
.. image:: media/process_manufacturing_orders_02.png
|
||||
:align: center
|
||||
|
||||
Manufacturing using routings can be broken down into several steps. When
|
||||
configuring your BoM, you will need to add a routing defining the
|
||||
component work orders. After planning the manufacturing order, you will
|
||||
have the added step of scheduling work orders.
|
||||
When manufacturing this way, each *Work Order* is scheduled
|
||||
individually. You will also have access to time and capacity planning,
|
||||
as well as reports on costing and efficiency for each *Work Center*.
|
||||
|
||||
The workflow is thus divided into three basic phases, as follows:
|
||||
.. image:: media/process_manufacturing_orders_03.png
|
||||
:align: center
|
||||
|
||||
1. Create manufacturing orders
|
||||
Thus, the workflow is divided into three basic phases:
|
||||
|
||||
2. Schedule the associated work orders.
|
||||
- Create the manufacturing order
|
||||
|
||||
3. Perform the scheduled work and record production.
|
||||
.. image:: media/process_manufacturing_orders_04.png
|
||||
:align: center
|
||||
|
||||
- Schedule the associated work orders
|
||||
|
||||
.. image:: media/process_manufacturing_orders_05.png
|
||||
:align: center
|
||||
|
||||
- Perform the scheduled work and record production
|
||||
|
||||
.. image:: media/process_manufacturing_orders_06.png
|
||||
:align: center
|
||||
|
After Width: | Height: | Size: 4.8 KiB |
|
After Width: | Height: | Size: 5.8 KiB |
|
After Width: | Height: | Size: 19 KiB |
|
After Width: | Height: | Size: 5.5 KiB |
|
After Width: | Height: | Size: 6.4 KiB |
|
After Width: | Height: | Size: 7.1 KiB |
|
After Width: | Height: | Size: 32 KiB |
|
After Width: | Height: | Size: 24 KiB |
|
After Width: | Height: | Size: 7.8 KiB |
|
After Width: | Height: | Size: 4.5 KiB |
|
After Width: | Height: | Size: 3.8 KiB |
|
After Width: | Height: | Size: 9.5 KiB |
|
After Width: | Height: | Size: 5.6 KiB |
|
After Width: | Height: | Size: 23 KiB |
|
After Width: | Height: | Size: 6.9 KiB |
|
After Width: | Height: | Size: 24 KiB |
|
Before Width: | Height: | Size: 6.7 KiB |
|
Before Width: | Height: | Size: 8.4 KiB |
|
Before Width: | Height: | Size: 9.6 KiB |
|
Before Width: | Height: | Size: 14 KiB |
|
Before Width: | Height: | Size: 11 KiB |
|
Before Width: | Height: | Size: 16 KiB |
|
After Width: | Height: | Size: 7.1 KiB |
|
After Width: | Height: | Size: 24 KiB |
|
After Width: | Height: | Size: 8.7 KiB |
|
After Width: | Height: | Size: 10 KiB |
|
After Width: | Height: | Size: 10 KiB |
|
After Width: | Height: | Size: 15 KiB |
|
After Width: | Height: | Size: 3.8 KiB |
|
After Width: | Height: | Size: 8.2 KiB |
|
After Width: | Height: | Size: 7.0 KiB |
|
After Width: | Height: | Size: 3.6 KiB |
|
After Width: | Height: | Size: 7.8 KiB |
|
After Width: | Height: | Size: 14 KiB |
|
After Width: | Height: | Size: 2.3 KiB |
|
After Width: | Height: | Size: 10 KiB |
|
After Width: | Height: | Size: 7.3 KiB |
|
After Width: | Height: | Size: 5.8 KiB |
|
After Width: | Height: | Size: 24 KiB |
|
After Width: | Height: | Size: 12 KiB |
|
After Width: | Height: | Size: 28 KiB |
|
After Width: | Height: | Size: 12 KiB |
|
Before Width: | Height: | Size: 2.6 KiB After Width: | Height: | Size: 2.6 KiB |
|
Before Width: | Height: | Size: 22 KiB After Width: | Height: | Size: 22 KiB |
|
Before Width: | Height: | Size: 12 KiB After Width: | Height: | Size: 12 KiB |
|
Before Width: | Height: | Size: 3.7 KiB After Width: | Height: | Size: 3.7 KiB |
|
Before Width: | Height: | Size: 12 KiB After Width: | Height: | Size: 12 KiB |
|
Before Width: | Height: | Size: 13 KiB After Width: | Height: | Size: 13 KiB |
|
Before Width: | Height: | Size: 12 KiB After Width: | Height: | Size: 12 KiB |
|
Before Width: | Height: | Size: 7.8 KiB After Width: | Height: | Size: 7.8 KiB |
|
After Width: | Height: | Size: 3.1 KiB |
|
After Width: | Height: | Size: 3.7 KiB |
|
After Width: | Height: | Size: 21 KiB |
|
After Width: | Height: | Size: 25 KiB |
|
After Width: | Height: | Size: 20 KiB |
|
After Width: | Height: | Size: 12 KiB |
|
After Width: | Height: | Size: 7.3 KiB |
|
After Width: | Height: | Size: 8.1 KiB |
|
After Width: | Height: | Size: 2.4 KiB |
@@ -0,0 +1,52 @@
|
||||
================
|
||||
Plan Work Orders
|
||||
================
|
||||
|
||||
In some cases, companies need to schedule their work orders. Doing so,
|
||||
they can organize the work for the whole day and be sure everything goes
|
||||
well. It helps to avoid scheduling multiple work orders at the same time
|
||||
when you don’t have the capacity to do so.
|
||||
|
||||
With Odoo, companies can schedule the planned start date for their
|
||||
manufacturing orders. No possible duplication, no potential issues with
|
||||
the planning. And, if you plan two work orders at the same work center,
|
||||
at the same hour, the second one will be scheduled right after the first
|
||||
one, avoiding work superposition.
|
||||
|
||||
Create the Work Orders
|
||||
======================
|
||||
|
||||
The first thing you need to do is to open the *Manufacturing* app.
|
||||
Then, Go to the settings and enable the *Work Orders* feature.
|
||||
|
||||
.. image:: media/plan_work_order_01.png
|
||||
:align: center
|
||||
|
||||
Now, go to the *Manufacturing Orders* menu and hit *Create*. Choose
|
||||
your product and add a *Planned Start Date*.
|
||||
|
||||
.. image:: media/plan_work_order_02.png
|
||||
:align: center
|
||||
|
||||
.. note::
|
||||
The “Deadline Start” field is informative. It shows you until when you
|
||||
can launch the manufacturing order to fulfill the initial demand.
|
||||
|
||||
Mark your *Manufacturing Order* as todo and plan it. By going to the
|
||||
*Planning* menu, you can access to the scheduled orders. Here is the
|
||||
one we just created:
|
||||
|
||||
.. image:: media/plan_work_order_03.png
|
||||
:align: center
|
||||
|
||||
.. note::
|
||||
If you plan two work orders at the same hour, the second one will be
|
||||
scheduled after the first one if the jobs need to be done at the same
|
||||
work center. The start date will, then, be automatically updated
|
||||
considering the first free slot on the work center.
|
||||
|
||||
If you overrun the planned date and begin the job later, you will have a
|
||||
track of it in the *Time Tracking* tab of your work order.
|
||||
|
||||
.. image:: media/plan_work_order_04.png
|
||||
:align: center
|
||||
@@ -1,42 +1,49 @@
|
||||
====================================
|
||||
How to manage semi-finished products
|
||||
====================================
|
||||
=============================
|
||||
Manage semi-finished products
|
||||
=============================
|
||||
|
||||
A subassembly is a manufactured product which is intended to be used as
|
||||
a component of another manufactured product. You may wish to employ
|
||||
sub-assemblies to simplify a complex BoM, to more accurately represent
|
||||
your manufacturing flow, or to use the same subassembly in multiple
|
||||
BoMs. A BoM that employs subassemblies is often referred to as a
|
||||
multi-level BoM.
|
||||
In Odoo, you can use subassembly products to simplify a complex *Bill
|
||||
of Materials* or to represent your manufacturing flow more accurately.
|
||||
A *subassembly product* is a manufactured product that is used as a
|
||||
component to make another one.
|
||||
|
||||
Multi-level bills of materials in Odoo are accomplished by creating a
|
||||
top-level BoM and subassembly BoMs. Next, the procurement route of the
|
||||
subassembly product is defined. This ensures that every time a
|
||||
manufacturing order for the top-level product is created, a
|
||||
manufacturing order for each subassembly is created as well.
|
||||
A *BoM* that employs *subassemblies* is referred to as a multi-level
|
||||
BoM. Those are accomplished by creating a *top-level BoM* and
|
||||
*subassembly ones*. This process requires a route that will ensure
|
||||
that every time a manufacturing order for the top-level product is
|
||||
created, another one will be for subassemblies.
|
||||
|
||||
Configure the Top -Level Product BoM
|
||||
------------------------------------
|
||||
Configure the Subassembly Product
|
||||
=================================
|
||||
|
||||
To configure a multi-level BoM, create the top-level product and its
|
||||
BoM. Include any subassemblies in the list of components. Create a BoM
|
||||
for each subassembly as you would for any product.
|
||||
To configure a *multi-level BoM*, you will need a top-level product
|
||||
but also its subassemblies. The first step is to create a product form
|
||||
for each of the subassemblies. Select the routes *Manufacture* and
|
||||
*Replenish on Order*. Now, hit save.
|
||||
|
||||
.. image:: media/sub_assemblies01.png
|
||||
.. image:: media/semi-finished_products_01.png
|
||||
:align: center
|
||||
|
||||
Configure the Subassembly Product Data
|
||||
--------------------------------------
|
||||
In the *Bill of Materials* menu, under *Master Data*, create a new
|
||||
*Bill of Materials*. Choose the product you just created and add its
|
||||
components.
|
||||
|
||||
On the product form of the subassembly, you must select the routes
|
||||
**Manufacture** and **Make To Order**. The **Manufacture**
|
||||
route takes precedence over the **Buy** route, so selecting the
|
||||
latter will have no effect.
|
||||
|
||||
.. image:: media/sub_assemblies02.png
|
||||
.. image:: media/semi-finished_products_02.png
|
||||
:align: center
|
||||
|
||||
If you would like to be able to purchase the subassembly in addition to
|
||||
manufacturing it, select **Can be Purchased**. All other fields on
|
||||
the subassembly product form may be configured according to your
|
||||
preference.
|
||||
Configure the Main BoM
|
||||
======================
|
||||
|
||||
Now, you can configure the top-level product and its *BoM*. Include
|
||||
any subassemblies in the list of components.
|
||||
|
||||
.. image:: media/semi-finished_products_03.png
|
||||
:align: center
|
||||
|
||||
Now, each time you will plan a manufacturing order for the top-level
|
||||
product, a manufacturing order will be created for the subassembly one.
|
||||
Then, you will have to manufacture the subassembly in order to make it
|
||||
available before manufacturing the finished product.
|
||||
|
||||
.. image:: media/semi-finished_products_04.png
|
||||
:align: center
|
||||
@@ -1,29 +1,35 @@
|
||||
Subcontract the manufacturing of some products
|
||||
==============================================
|
||||
=============================
|
||||
Subcontract the manufacturing
|
||||
=============================
|
||||
|
||||
Some business subcontract the production of some finished products
|
||||
Some businesses subcontract the production of some finished products
|
||||
through subcontractors. This can be easily managed through Odoo.
|
||||
|
||||
Configuration
|
||||
-------------
|
||||
=============
|
||||
|
||||
Go in the :menuselection:`Manufacturing --> Configuration --> Settings` and tick the box *Subcontracting*.
|
||||
Go to the *Manufacturing app > Configuration > Settings* and tick the
|
||||
box *Subcontracting*.
|
||||
|
||||
.. image:: media/subcontracting01.png
|
||||
.. image:: media/subcontract_01.png
|
||||
:align: center
|
||||
|
||||
You can now define subcontractors contacts. When you purchase or receive
|
||||
products from a contact of type subcontractor, the correct stock moves
|
||||
are created to represent the subcontracting of the production.
|
||||
|
||||
.. image:: media/subcontracting02.png
|
||||
.. image:: media/subcontract_02.png
|
||||
:align: center
|
||||
|
||||
The next step is to create a Bill of Material of type *subcontracted*.
|
||||
In this BoM, list the components you need to supply to the
|
||||
subcontractor.
|
||||
.. tip::
|
||||
You can set the subcontractor as a vendor in case you plan to buy him
|
||||
the subcontracted products via purchase orders.
|
||||
|
||||
.. image:: media/subcontracting03.png
|
||||
The next step is to create a *Bill of Material* of type
|
||||
*subcontracted*. In this *BoM*, list the components you need to
|
||||
supply to the subcontractor.
|
||||
|
||||
.. image:: media/subcontract_03.png
|
||||
:align: center
|
||||
|
||||
You can also define subcontractors on the BoM.
|
||||
@@ -32,76 +38,77 @@ You can also define subcontractors on the BoM.
|
||||
|
||||
- If some are set, the BoM can only be used for those subcontractors
|
||||
|
||||
.. image:: media/subcontracting04.png
|
||||
.. image:: media/subcontract_04.png
|
||||
:align: center
|
||||
|
||||
The configuration part is already done!
|
||||
|
||||
Receive or buy a subcontracted product
|
||||
--------------------------------------
|
||||
======================================
|
||||
|
||||
You have two options to trigger a the subcontracting of a product:
|
||||
You have two options to trigger the subcontracting of a product:
|
||||
|
||||
- Option A: You can buy the subcontracted product from your
|
||||
- **Option A**: You can buy the subcontracted product from your
|
||||
subcontractor
|
||||
|
||||
- Option B: You can directly receive the subcontracted product
|
||||
- **Option B**: You can directly receive the subcontracted product
|
||||
|
||||
Let’s start with option A (option B is just a simpler version of it).
|
||||
|
||||
Create a new purchase order. The vendor must be a subcontractor. The
|
||||
unit price should be the cost you are paying to the subcontractor for
|
||||
the subcontracting (it’s thus not necessarily the total cost of the
|
||||
the subcontracting (thus, it’s not necessarily the total cost of the
|
||||
subcontracted product).
|
||||
|
||||
.. image:: media/subcontracting05.png
|
||||
.. image:: media/subcontract_05.png
|
||||
:align: center
|
||||
|
||||
The validation of the purchase order creates automatically the receipt.
|
||||
The validation of the purchase order automatically creates the receipt.
|
||||
Whenever you receive the product, you can validate the receipt. The
|
||||
following stock moves are created:
|
||||
|
||||
- For the components
|
||||
|
||||
From Subcontracting To Production
|
||||
- From Subcontracting To Production
|
||||
|
||||
- For the subcontracted product
|
||||
|
||||
From Production to Subcontracting
|
||||
- From Production to Subcontracting
|
||||
|
||||
From Subcontracting to Stock
|
||||
- From Subcontracting to Stock
|
||||
|
||||
The *Subcontracting Location* represents the place where the products
|
||||
are at your subcontractor’s warehouse. It is configured as an internal
|
||||
location, the components that are sent to the subcontractor are still
|
||||
valued in your stock.
|
||||
|
||||
For option B, you simply can create the receipt manually with a partner
|
||||
For option B, you can simply create the receipt manually with a partner
|
||||
of type subcontractor defined on it.
|
||||
|
||||
Resupply the subcontractor with the components
|
||||
----------------------------------------------
|
||||
==============================================
|
||||
|
||||
There are 3 ways to manage the resupply of your subcontractor with the
|
||||
components:
|
||||
|
||||
- Manually. You simply create a delivery order on which you set the
|
||||
subcontractor as partner and you choose the components to deliver
|
||||
- **Manually**: You create a delivery order in which you set the
|
||||
subcontractor as a partner and you choose the components to
|
||||
deliver.
|
||||
|
||||
.. image:: media/subcontracting06.png
|
||||
.. image:: media/subcontract_06.png
|
||||
:align: center
|
||||
|
||||
- With reordering rules. You can define a reordering rule on the
|
||||
Subcontracting location to ensure that they are always enough
|
||||
components send to your subcontractors.
|
||||
- **With reordering rules**: You can define a *reordering rule*
|
||||
on the *Subcontracting location* to ensure that they are always
|
||||
enough components sent to your subcontractors. When the
|
||||
reordering rule is triggered, a delivery order is created for the
|
||||
product is automatically created.
|
||||
|
||||
.. image:: media/subcontracting07.png
|
||||
.. image:: media/subcontract_07.png
|
||||
:align: center
|
||||
|
||||
- On order. You can also deliver the components to your subcontractors
|
||||
each time you order a subcontracted product. For this, you need
|
||||
to tick the route “Resupply Subcontractor on Order” on the
|
||||
components concerned.
|
||||
- **On order**: You can also deliver the components to your
|
||||
subcontractors each time you order a subcontracted product. For
|
||||
this, you need to tick the route *Resupply Subcontractor on
|
||||
Order* on the wanted components.
|
||||
|
||||
.. image:: media/subcontracting08.png
|
||||
:align: center
|
||||
.. image:: media/subcontract_08.png
|
||||
:align: center
|
||||
@@ -0,0 +1,125 @@
|
||||
==================================
|
||||
Use the Master Production Schedule
|
||||
==================================
|
||||
|
||||
The Master Production Schedule (MPS) is a valuable tool to plan your
|
||||
production based on your demand forecast.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
Go to the *Manufacturing app > Configuration > Settings* and activate
|
||||
the Master Production Schedule feature before hitting save.
|
||||
|
||||
.. image:: media/use_mps_01.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
In the manufacturing settings, you can define the time range of your MPS (month/week/day) and the number of periods you want to display.
|
||||
|
||||
Now, go in *Planning > Master Production Schedule* and click on add a
|
||||
product. You can now define your safety stock target (= the stock you
|
||||
want to have on hand at the end of the period) and the minimum and
|
||||
maximum quantities to replenish.
|
||||
|
||||
.. image:: media/use_mps_02.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
The products are ordered in the MPS based on their sequence. You can
|
||||
rearrange that sequence by going on the list of your products and
|
||||
reorganize them with drag and drop.
|
||||
|
||||
.. image:: media/use_mps_03.png
|
||||
:align: center
|
||||
|
||||
In the MPS view, you can decide which information you would like to show
|
||||
by clicking on *rows*. Some fields can be added to the view, such as
|
||||
*Actual demand*, which will show which quantity of products has
|
||||
already been ordered for the period, or *Available to Promise*, which
|
||||
allows you to know what can still be sold during the period (what you
|
||||
plan to replenish - what is already sold during the period). You can
|
||||
also decide to hide some information if it isn’t necessary.
|
||||
|
||||
.. image:: media/use_mps_04.png
|
||||
:align: center
|
||||
|
||||
Estimate your demand and launch replenishment
|
||||
=============================================
|
||||
|
||||
The next step is to estimate the demand for the period. This estimation
|
||||
should be entered in the row *Demand Forecast*. You can easily, at any
|
||||
time, compare the demand forecast with the actual demand (= confirmed
|
||||
sales). The demand forecast for a finished product will impact the
|
||||
indirect demand for its components.
|
||||
|
||||
.. image:: media/use_mps_05.png
|
||||
:align: center
|
||||
|
||||
Then, the quantity to replenish for the different periods will be
|
||||
automatically computed. The replenishments you are supposed to launch
|
||||
based on your lead times (vendor lead time or manufacturing lead time)
|
||||
are displayed in green. You can now launch the replenishment by clicking
|
||||
on the replenish button.
|
||||
|
||||
Depending on the configuration of the product (buy vs. manufacture),
|
||||
requests for quotations or manufacturing orders will be created. You can
|
||||
easily access those by clicking on the *Actual Replenishment* cell.
|
||||
|
||||
.. image:: media/use_mps_06.png
|
||||
:align: center
|
||||
|
||||
.. image:: media/use_mps_07.png
|
||||
:align: center
|
||||
|
||||
In case you manually edit the *To replenish* quantity, a small cross
|
||||
will appear on the left. In case you want to go back to the
|
||||
automatically computed value given by Odoo, you can click the cross.
|
||||
|
||||
.. image:: media/use_mps_08.png
|
||||
:align: center
|
||||
|
||||
Cells color signification
|
||||
=========================
|
||||
|
||||
The cells, which are part of the *To replenish* line, can take
|
||||
different colors depending on the situation:
|
||||
|
||||
- **Green**: quantity of products which should be replenished to
|
||||
reach the expected safety stock considering the demand forecast
|
||||
and the indirect demand forecast.
|
||||
|
||||
- **Grey**: replenishment order has already been generated, and its
|
||||
quantity still matches current data.
|
||||
|
||||
- **Red**: replenishment order has already been generated, and its
|
||||
quantity was too high considering current data.
|
||||
|
||||
- **Orange**: replenishment order has already been generated, and
|
||||
its quantity was too low considering current data.
|
||||
|
||||
The *Forecasted stock* line can also contain red cells, which means
|
||||
the stock will be negative during the period in question.
|
||||
|
||||
What if I have underestimated the demand?
|
||||
-----------------------------------------
|
||||
|
||||
You can still increase the demand forecast. It will impact the quantity
|
||||
to replenish. The cell will become orange, and you’ll be able to launch
|
||||
a new replenishment.
|
||||
|
||||
What if I have overestimated the demand?
|
||||
----------------------------------------
|
||||
|
||||
You can decrease the demand forecast. The cell will become red to inform
|
||||
you that you’ve ordered more than planned. If you’re still able to do
|
||||
it, you can cancel some RFQ or MO manually.
|
||||
|
||||
What if I wrongly added a product to the MPS?
|
||||
---------------------------------------------
|
||||
|
||||
You can easily remove a product from the MPS by clicking the small bin
|
||||
on the right of its name.
|
||||
|
||||
.. image:: media/use_mps_09.png
|
||||
:align: center
|
||||