[REF] mrp: documentation update
- Updated Pictures with latest version, deleted old ones
- Added Quality Control section
- Deleted Kit Routings section
- Adapted Terminology, specifically work orders vs routings
closes odoo/documentation#1535
X-original-commit: 6fb40b61c8
Signed-off-by: Antoine Vandevenne (anv) <anv@odoo.com>
Signed-off-by: Arnold Moyaux <arm@odoo.com>
This commit is contained in:
committed by
Arnold Moyaux
parent
8966e001c2
commit
42bef26a5d
+102
-120
@@ -2,16 +2,13 @@
|
||||
Subcontract your Manufacturing
|
||||
==============================
|
||||
|
||||
Outsourcing a portion of some or all your company’s manufacturing needs
|
||||
is not easy. To make it work right, you have to:
|
||||
Outsourcing a portion or all of your company’s manufacturing needs
|
||||
is not easy. To make it work correctly, you have to:
|
||||
|
||||
- Manage the inventory of raw materials at your subcontractor;
|
||||
- Ship new materials to your subcontractors based on your forecasted
|
||||
demand;
|
||||
- Keep track of manufacturing operations done at the subcontractor
|
||||
location;
|
||||
- Control incoming goods quality;
|
||||
- Control subcontractors bills.
|
||||
- Manage the inventory of raw materials at your subcontractor
|
||||
- Ship raw material to your subcontractors, at the right time
|
||||
- Control incoming goods quality
|
||||
- Control subcontractors bills
|
||||
|
||||
Here is an example of subcontracting the manufacturing of “C”, which is
|
||||
produced out of raw materials “A” and “B”.
|
||||
@@ -20,7 +17,7 @@ produced out of raw materials “A” and “B”.
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
With its subcontracting feature, Odoo helps you handle this flow easily.
|
||||
With its MRP subcontracting feature, Odoo helps you handle this flow easily.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
@@ -28,15 +25,15 @@ Configuration
|
||||
To use the subcontracting feature, go to :menuselection:`Manufacturing
|
||||
--> Configuration --> Settings` and tick the box *Subcontracting*.
|
||||
|
||||
.. image:: media/subcontracting_02.png
|
||||
.. image:: media/sbc_1.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
To define if a product must be subcontracted, use a *Bill of Materials
|
||||
(BoM)* of type *Subcontracting*.
|
||||
|
||||
To create a new *BoM*, go to :menuselection:`Manufacturing --> Master
|
||||
Data --> Bill of Materials` and hit create. Then, list the components
|
||||
To create a new *BoM*, go to :menuselection:`Manufacturing --> Products -->
|
||||
Bill of Materials` and hit create. Then, list the components
|
||||
your subcontractor needs to manufacture the product. For costing
|
||||
purposes, you might want to register all the components, even the ones
|
||||
that are sourced directly from the subcontractor.
|
||||
@@ -44,7 +41,7 @@ that are sourced directly from the subcontractor.
|
||||
Once you have set the *BoM Type* to *Subcontracting*, specify one or
|
||||
several subcontractors.
|
||||
|
||||
.. image:: media/subcontracting_03.png
|
||||
.. image:: media/sbc_2.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
@@ -52,9 +49,9 @@ Basic Subcontracting Flow
|
||||
=========================
|
||||
|
||||
To let your subcontractor know how many products you need, create and
|
||||
send them purchase orders (PO). To do so, open the *Purchase* app and
|
||||
create a new one. Be sure to send the PO to a vendor that is defined as
|
||||
a subcontractor on the *BoM*.
|
||||
send them purchase orders (PO). To do so, go to the *Purchase* app and
|
||||
create a new purchase order. Be sure to send the PO to a vendor that is
|
||||
defined as a subcontractor on the *BoM* of these products.
|
||||
|
||||
.. image:: media/subcontracting_04.png
|
||||
:align: center
|
||||
@@ -62,23 +59,20 @@ a subcontractor on the *BoM*.
|
||||
|
||||
Once the *PO* is validated (1), a pending receipt is created. When the
|
||||
products are received, validate the receipt (2), with the actual
|
||||
quantity received. Then Odoo automatically created several inventory
|
||||
moves:
|
||||
quantity received. As a result, Odoo does the following things for you:
|
||||
|
||||
- Consume the components at the subcontractor’s location, based on the
|
||||
*BoM* (3);
|
||||
- Produce finished goods at the subcontractor’s location (4);
|
||||
- Move products from the subcontractor’s location to YourCompany
|
||||
through the validated receipt (5).
|
||||
- Consumes the respective components at the subcontractor’s location, based on the *BoM* and your input (3);
|
||||
|
||||
- Produces the finished goods at the subcontractor’s location (4);
|
||||
|
||||
- Moves products from that subcontractor’s location to YourCompany
|
||||
via the validated receipt (5).
|
||||
|
||||
Of course, Odoo does all the transactions for you, automatically. Simply
|
||||
control the vendor bill with the usual matching process with the
|
||||
purchase order.
|
||||
|
||||
.. note::
|
||||
The *PO* is optional. If you create a receipt manually, with the right
|
||||
subcontractor, Odoo still performs all the moves. Useful if the
|
||||
subcontractor does not bill a fixed price per item, but rather the time
|
||||
subcontractor, Odoo still performs all the moves. This can be useful if
|
||||
the subcontractor does not bill a fixed price per item, but rather the time
|
||||
and materials used.
|
||||
|
||||
Inventory Valuation
|
||||
@@ -98,18 +92,17 @@ With:
|
||||
- **s**: Cost of the subcontracted service.
|
||||
|
||||
Sending raw materials to your subcontractors (**A**) does not impact
|
||||
the inventory valuation, the components still belonging to your company.
|
||||
To manage this, the *Subcontracting Location* is configured as an
|
||||
*Internal Location* so that the components are still valued in the
|
||||
inventory.
|
||||
the inventory valuation, as the components are still valued as part of
|
||||
your stock. This is managed by making the *Subcontracting Location* an
|
||||
*Internal Location*.
|
||||
|
||||
Then, the vendor price set on the product C form has to be what has to
|
||||
be paid to the subcontractor for his parts and service time: **B +
|
||||
s**. The product cost has to be: **A + B + s**, how much the
|
||||
product is valued in the accounting.
|
||||
|
||||
Finally, the subcontractor bill matches the purchase order, with the
|
||||
proposed price coming from the finished products C.
|
||||
Finally, the subcontractor bill then matches the purchase order, with
|
||||
the proposed price coming from the finished products C.
|
||||
|
||||
.. note::
|
||||
If managing the replenishment of raw materials **B** at your
|
||||
@@ -120,113 +113,102 @@ proposed price coming from the finished products C.
|
||||
Traceability
|
||||
============
|
||||
|
||||
In case the products received from the subcontractor contain tracked
|
||||
In case the received products from the subcontractor contain tracked
|
||||
components, their serial or lot numbers need to be specified during the
|
||||
receipt.
|
||||
receipt.
|
||||
|
||||
On the receipt of the subcontracted product, a *Record Components*
|
||||
button appears when necessary. Click on it to open a dialog and record
|
||||
the serial/lot numbers of the components. If the finished product is
|
||||
also tracked, its serial/lot number can be registered here too.
|
||||
In that case, on the receipt of the subcontracted product, a *Record Components*
|
||||
button appears. Click on it to open a dialog box and record the serial/lot numbers of
|
||||
the components. If the finished product is also tracked, its serial/lot number can
|
||||
be registered here too.
|
||||
|
||||
.. image:: media/subcontracting_05.png
|
||||
.. image:: media/sbc_3.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
For audit purposes, it is possible to check the lot numbers recorded on
|
||||
a receipt by using the icon on the right of the finished products:
|
||||
|
||||
.. image:: media/subcontracting_06.png
|
||||
.. image:: media/sbc_4.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
Also note that in case flexible consumption has been selected on the subcontracted
|
||||
BOM for a non-tracked product, the record components option will also appear
|
||||
optionally on each move line, if you want to register more or less component consumption
|
||||
at your subcontracting location, when receiving your final product.
|
||||
|
||||
.. image:: media/sbc_5.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
As you can see, the reception of both of these non-tracked products can either be executed
|
||||
by selecting the 'Set Quantities' Option or via the move line hamburger menus.
|
||||
|
||||
Automate Replenishment of Subcontractors
|
||||
========================================
|
||||
|
||||
To manage the resupply of your subcontractor, activate
|
||||
*Multi-locations* in :menuselection:`Inventory --> Configuration -->
|
||||
Configuration`. Then, the inventory at the subcontractor location can
|
||||
be tracked.
|
||||
There are two ways to automate the supply of raw materials to your
|
||||
subcontractors when purchasing the final product. The chosen method
|
||||
depends on whether or not you want the materials to transit through your
|
||||
warehouse. Both of these methods are described as pull style mechanisms as
|
||||
their trigger is the inital PO to the subcontractor, which creates a need
|
||||
at the subcontracting location, for raw material.
|
||||
|
||||
It is possible to resupply subcontractors by sending products from the
|
||||
company locations, or by sending products from another supplier to the
|
||||
subcontractors.
|
||||
If you are supplying your subcontractor with raw material from your own warehouse,
|
||||
you must activate the 'Resupply Subcontractor on Order' route as shown
|
||||
below. If this is a component that you buy from a vendor, the buy route
|
||||
should also be activated.
|
||||
|
||||
Replenishment from the warehouse
|
||||
|
||||
.. image:: media/sbc_6.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
|
||||
Now, if you want your vendor to resupply your subcontractor directly, you
|
||||
must choose the 'Dropship Subcontractor on Order' option instead. In order
|
||||
for this option to be active on the product form, you must first activate the
|
||||
dropship option from :menuselection:`Purchase --> Configuration --> Settings -->
|
||||
Dropshipping`.
|
||||
Once the PO to the subcontractor is validated, this route will create a dropship
|
||||
RFQ from your vendor to that subcontractor. You then just need to review and validate it.
|
||||
|
||||
|
||||
.. image:: media/sbc_7.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
Note that the buy route is not selected in this case, as the dropship route is
|
||||
a buy route already.
|
||||
|
||||
Finally, if you want to track the stock of these raw materials at your subcontracting
|
||||
location(s), then you must activate *Multi-locations* in :menuselection:`Inventory -->
|
||||
Configuration --> Settings --> Storage locations`.
|
||||
|
||||
From the location form, you are then able to access the Current Stock.
|
||||
|
||||
.. image:: media/sbc_8.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
|
||||
|
||||
Manual Replenishment
|
||||
--------------------------------
|
||||
|
||||
Resupplying subcontractors manually is the simplest approach. To do so,
|
||||
create delivery orders in which the subcontractor is set as a delivery
|
||||
address and fill the components to deliver.
|
||||
You can also choose to replenish your subcontractors manually.
|
||||
|
||||
To automate the subcontractors’ replenishment propositions, there are
|
||||
two approaches:
|
||||
If you want to send components to your subcontractor at your own convenience,
|
||||
select the 'Resupply Subcontractor' Operation Type from the *Inventory* Module,
|
||||
and create a picking, specifying to which subcontractor you are delivering to.
|
||||
|
||||
- Reordering rules;
|
||||
- Replenish on order flow.
|
||||
|
||||
For the first one, just define a reordering rule on the subcontracting
|
||||
location, with a minimum and maximum inventory level. When the
|
||||
reordering rule is triggered, a delivery order is created to ship the
|
||||
components to the subcontractor.
|
||||
|
||||
.. image:: media/subcontracting_07.png
|
||||
.. image:: media/sbc_9.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
The second approach is to use a “pull” flow. Here, the demand in the
|
||||
finished product (real demand or forecasted one through the Master
|
||||
Production Schedule) triggers the replenishment of the subcontractor. To
|
||||
do so, select the route *Resupply Subcontractor on Order* on the
|
||||
wanted components.
|
||||
Alternatively, you can also manually ask your vendor to resupply your subcontractor
|
||||
by creating a dropship type PO, with your subcontractor set as the delivery address.
|
||||
|
||||
.. image:: media/subcontracting_08.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
Replenishment from another supplier
|
||||
-----------------------------------
|
||||
|
||||
When purchasing items to another supplier, it is possible to ask him to
|
||||
deliver the subcontractor directly. To do so, activate the *Drop
|
||||
Shipping* feature in :menuselection:`Purchase --> Configuration -->
|
||||
Configuration`.
|
||||
|
||||
Now, set the *Dropship* option in the *Deliver To* field of the
|
||||
*Other Information* tab. Then, provide the address of the
|
||||
subcontractor for the shipping.
|
||||
|
||||
.. image:: media/subcontracting_09.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
That way, the supplier can ship items directly and you simply receive
|
||||
and pay the bill. However, it is still required to validate receipts for
|
||||
the subcontractor.
|
||||
|
||||
.. image:: media/subcontracting_10.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
Quality Control
|
||||
---------------
|
||||
|
||||
Controlling the quality of the products manufactured by subcontractors
|
||||
is possible thanks to the Odoo Quality app. Quality checks can be made
|
||||
on a manufacturing step but, because the manufacturing process is
|
||||
handled by an external party, it can be defined on the product
|
||||
reception.
|
||||
|
||||
.. image:: media/subcontracting_11.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
To create a quality check at the receipt, open the *Quality* app and
|
||||
create a new *Control Point* on the reception.
|
||||
|
||||
.. image:: media/subcontracting_12.png
|
||||
:align: center
|
||||
:alt:
|
||||
|
||||
By doing so, a quality check is automatically created each time a
|
||||
finished product is received.
|
||||
.. image:: media/sbc_10.png
|
||||
:align: center
|
||||
Reference in New Issue