Schedule your receipts and deliveries
|
|
|
|
|
|
=====================================
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
To manage your supply chain scheduling, you will need to use Odoo *Lead
|
|
|
|
|
|
Times*.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
*Lead Times* are the expected times needed to receive, deliver or
|
|
|
|
|
|
manufacture products.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Configure Lead Times
|
|
|
|
|
|
====================
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Vendor Lead Time
|
|
|
|
|
|
----------------
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
The vendor lead time is the time needed by your vendor to deliver the
|
|
|
|
|
|
product to you.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
To configure your vendor lead times, go to a product page, under the
|
|
|
|
|
|
purchase tab, click on a *Vendor* once there you can change the
|
|
|
|
|
|
delivery lead time for that Vendor & Product.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
.. image:: media/compute_date01.png
|
|
|
|
|
|
:align: center
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Customer Lead Time
|
|
|
|
|
|
------------------
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
The customer lead time, on the other hand, is the time you need to
|
|
|
|
|
|
deliver the product to your customer.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
To configure your customer lead time open a product and go under the
|
|
|
|
|
|
*Inventory* tab. You can then add how many days you need.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
.. image:: media/compute_date02.png
|
|
|
|
|
|
:align: center
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Manufacturing lead time
|
|
|
|
|
|
-----------------------
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
The manufacturing lead time is the time you need to manufacture the
|
|
|
|
|
|
product.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
To configure your manufacturing lead time open a product and go under
|
|
|
|
|
|
the *Inventory* tab. You can then add how many days you need.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
.. image:: media/compute_date03.png
|
|
|
|
|
|
:align: center
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Configure Security Lead Times
|
|
|
|
|
|
=============================
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Odoo also lets you configure *Security Days* allowing you to cope with
|
|
|
|
|
|
potential delays along the supply chain and make sure you meet your
|
|
|
|
|
|
engagements.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
The easiest way is to go to *Settings* from any module and type
|
|
|
|
|
|
**Lead Time** in the search bar. From there, tick each box and
|
|
|
|
|
|
configure your various *Security Lead Time* for your needs.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
.. image:: media/compute_date04.png
|
|
|
|
|
|
:align: center
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Alternatively, you can go in the settings of the *Inventory* module
|
|
|
|
|
|
and *Manufacturing* module to configure those settings.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
Lead & security times in a use case
|
|
|
|
|
|
===================================
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
For example you sell a car today (January 1st), that is purchased on
|
|
|
|
|
|
order, and you promise to deliver your customer within 20 days (January
|
|
|
|
|
|
20). Here is your product’s configuration:
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- Security lead time for sales : 1 day
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- Security lead time for purchase : 1 day
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- Vendor delivery lead time : 9 days
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
In such a scenario, the scheduler will trigger the following events
|
|
|
|
|
|
based on your configuration.
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- January 19: scheduled delivery date (20th January - 1 day of security
|
|
|
|
|
|
lead time for Sales)
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- January 18: scheduled receipt date (19th January - 1 day of security
|
|
|
|
|
|
lead time for Purchase)
|
2015-11-05 14:09:37 +01:00
|
|
|
|
|
2018-05-11 10:11:02 +02:00
|
|
|
|
- January 10: order date = deadline to order from your vendor (19th
|
|
|
|
|
|
January - 9 days of vendor lead time)
|