Plan Work Orders
|
|||
|
|
================
|
|||
|
|
|
|||
|
|
In some cases, companies need to schedule their work orders. Doing so,
|
|||
|
|
they can organize the work for the whole day and be sure everything goes
|
|||
|
|
well. It helps to avoid scheduling multiple work orders at the same time
|
|||
|
|
when you don’t have the capacity to do so.
|
|||
|
|
|
|||
|
|
With Odoo, companies can schedule the planned start date for their
|
|||
|
|
manufacturing orders. No possible duplication, no potential issues with
|
|||
|
|
the planning. And, if you plan two work orders at the same work center,
|
|||
|
|
at the same hour, the second one will be scheduled right after the first
|
|||
|
|
one, avoiding work superposition.
|
|||
|
|
|
|||
|
|
Create the Work Orders
|
|||
|
|
======================
|
|||
|
|
|
|||
|
|
The first thing you need to do is to open the *Manufacturing* app.
|
|||
|
|
Then, Go to the settings and enable the *Work Orders* feature.
|
|||
|
|
|
|||
|
|
.. image:: media/plan_work_order_01.png
|
|||
|
|
:align: center
|
|||
|
|
|
|||
|
|
Now, go to the *Manufacturing Orders* menu and hit *Create*. Choose
|
|||
|
|
your product and add a *Planned Start Date*.
|
|||
|
|
|
|||
|
|
.. image:: media/plan_work_order_02.png
|
|||
|
|
:align: center
|
|||
|
|
|
|||
|
|
.. note::
|
|||
|
|
The “Deadline Start” field is informative. It shows you until when you
|
|||
|
|
can launch the manufacturing order to fulfill the initial demand.
|
|||
|
|
|
|||
|
|
Mark your *Manufacturing Order* as todo and plan it. By going to the
|
|||
|
|
*Planning* menu, you can access to the scheduled orders. Here is the
|
|||
|
|
one we just created:
|
|||
|
|
|
|||
|
|
.. image:: media/plan_work_order_03.png
|
|||
|
|
:align: center
|
|||
|
|
|
|||
|
|
.. note::
|
|||
|
|
If you plan two work orders at the same hour, the second one will be
|
|||
|
|
scheduled after the first one if the jobs need to be done at the same
|
|||
|
|
work center. The start date will, then, be automatically updated
|
|||
|
|
considering the first free slot on the work center.
|
|||
|
|
|
|||
|
|
If you overrun the planned date and begin the job later, you will have a
|
|||
|
|
track of it in the *Time Tracking* tab of your work order.
|
|||
|
|
|
|||
|
|
.. image:: media/plan_work_order_04.png
|
|||
|
|
:align: center
|